Fulton Street Road Construction

It is anticipated that this City of Grand Rapids telecommunication duct bank and street lighting project will begin February 22nd with completion in May 2012. A separate City of Grand Rapids resurfacing project will start in May with completion by the end of June 2012.

If you have questions or concerns, please contact project staff listed below:
Jeremy Kramer City's Consulting Engineer jnkramer@ftch.com 464-3923

John Brom Construction Inspection Supervisor jbrom@grcity.us 456-3076


PROJECT FACTS

IMPROVEMENTS IN FULTON STREET (Feb. 2012 THROUGH May 2012) - SCOPE OF WORK:

Reconstruct approximately 1000' of telecommunications duct bank and rehabilitate existing street lighting.

In conjunction with the City's street lighting telecommunications duct bank and street lighting rehabilitation, Consumers Energy will also be reconstructing approximately 1000' of electrical duct bank within the project limits.

ACCESS/DETOURS

Phasing has been adjusted to shorten the duration of the project. Phase 1 will begin with a through traffic closure at the Fulton and Monroe/Market intersection for approximately three weeks. Phase 2 will occur in the Ottawa and Fulton intersection for two additional weeks. (see attached info)

Phase 3 (Mar 30 to May 4): One lane of traffic in each direction of Fulton will be maintained with intermittent intersection closures and north/south detours at Ionia, Commerce and Division.

Phase 4 (May 12 to May 30) Fulton from the Grand River to just east of the Ottawa intersection will be closed to traffic to place concrete white topping.

Phase 5 (June 4 to June 23) Fulton Street from just east of the Ottawa intersection to Division will be closed to traffic to place concrete white topping.

OTHER NOTES:

Pedestrian access will be maintained. Local access will be maintained outside of the work zone.

EVENING and WEEKEND CITY EMERGENCY NUMBER: 456-3249 Si usted necesita hablar con alguien en español acerca de este proyecto, llame a Carlos Sanchez al teléfono 481-1548.


See attached map (PDF)

Wednesday, February 22, 2012
 All Day Event

Categories:

Location:
 
Fulton Street between the Grand River & Division
Fulton Street West & Monroe Ave NW
Grand Rapids, MI 49503

Event Contact Info
Website:
 Click to Visit